home construction timeline
We’re building a Columbia Elevation B with Ryan Homes!
Click on the dates on the left-hand side to learn more about the process if applicable.
Homesite Reservation | Selecting Options
Purchase Agreement
7 Day Structural Change Deadline
Meeting with NVR Mortgage Loan Officer
Blog post to come.
Interior Selections
Cabinets, Countertops, and Flooring— oh my!
Secured Pre-Approval for Mortgage with NVR
No blog post.
21 Day Flooring, Wiring, Non-Structural Change Deadline
Blog post to come.
Foundation Dug
No blog post.
Footers Completed
This was done during the week.
Foundation Wall Forms Set
No blog post.
Pre-Construction Meeting
Blog post to come.
Foundation Walls Poured
No blog post.
Foundation Wall Forms Removed
No blog post.
Waterproofing and Drains Added
No blog post.
Some Backfill, Weeping Tile and Crushed Gravel Added
No blog post.
Independent Foundation Inspection
No blog post.
Floor Joists and Floor Sheeting Added
No blog post.
Main Floor Framing Done
No blog post.
Second Floor Framing Done
No blog post.
Roof Framing Done
No blog post.
Shingles Done
No blog post.
HVAC, Plumbing, Electricals Finished
No blog post. Note that most of this was finished, but there were still a few loose ends to tie up.
Independent Home Inspection
Blog post TBD.
Insulation Added
No blog post.
Pre-Drywall Meeting
Blog post to come.
Drywall Added and Sealed
No blog post.
Exterior Vinyl Siding Added
There was some documentation mismatch. The vinyl might be replaced due to the incorrect color.
Cabinets and Trim Installed
No blog post.
Fixtures Installed, Walls Painted
No blog post.
Cement Sidewalk Poured and Finished
No blog post.
Exterior Stone Added, Front Door Painted
No blog post.
Door Hardware Installed, Vinyl Flooring Installed
No blog post.
Electric, Gas, Water Hook-Ups Finished
No blog post.
Carpet and final trim pieces installed
No blog post.
Landscaping Added
No blog post.
Asphalt Paved
No blog post.
Backsplash Added
No blog post.
All appliances (Gas Range, Range Hood, Dishwasher, Microwave) installed
No blog post.
Nema 14-50R outlet installed
No blog post.
Home Cleaning & Ryan Homes Inspections finished
No blog post.